The Journey of Creating a Stunning Detached ADU in Toluca Lake, California
Jul 29, 2024
1 min read
0
19
0
Week 2: Site Preparation and Foundation Work
This week marked significant progress on our Toluca Lake ADU project. Here's what we've accomplished:
Survey and Underground Plumbing
We began by conducting a thorough site survey to ensure accurate measurements and proper planning. With the survey completed, we moved on to forming the structure and laying down the underground plumbing. Proper installation of plumbing is crucial at this stage to avoid any issues down the line.
Foundation Preparation
With the underground plumbing in place, we started preparing for the foundation. Our team worked meticulously to ensure that the foundation is both sturdy and level, setting the stage for a solid build.
Cement Work
By the end of the week, we began the process of pouring cement for the foundation. This is a critical step that will provide the necessary support for the entire structure. We ensured that the cement work was done with precision to create a strong and durable base for the ADU.
Stay tuned for next week’s update, where we will detail the progress on framing the structure and further developments in our Toluca Lake ADU project!